Q1A can complete a piece of work in 12 days, and B can complete the same work in 24 days. If they work together, how many days will it take them to complete the work?
A
6 days
B
8 days
C
10 days
D
14 days
Correct Answer: B
Explanation
A's 1-day work = 1/12, B's 1-day work = 1/24. Combined 1-day work = 1/12 + 1/24 = 3/24 = 1/8. Therefore, they will complete the work together in 8 days.
Q2A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work?
A
9 days
B
12 days
C
15 days
D
20 days
Correct Answer: A
Explanation
Combined 1-day work = 1/6. A's 1-day work = 1/18. B's 1-day work = 1/6 - 1/18 = 2/18 = 1/9. Therefore, B alone can complete the work in 9 days.
Q3A is twice as efficient as B. If they complete a piece of work together in 14 days, how many days will A alone take to finish it?
A
21 days
B
28 days
C
42 days
D
35 days
Correct Answer: A
Explanation
Let B's efficiency be 1 unit/day, so A's efficiency is 2 units/day. Combined efficiency = 3 units/day. Total work = 3 * 14 = 42 units. Time taken by A alone = 42 / 2 = 21 days.
Q412 men can complete a work in 8 days. How many days will 16 men take to complete the same work?
A
4 days
B
5 days
C
6 days
D
7 days
Correct Answer: C
Explanation
Using the formula M1 * D1 = M2 * D2: 12 * 8 = 16 * D2. 96 = 16 * D2. D2 = 96 / 16 = 6 days.
Q5A, B, and C can complete a work in 10, 12, and 15 days respectively. If they all work together, how long will they take to finish the work?
A
3 days
B
4 days
C
5 days
D
6 days
Correct Answer: B
Explanation
Total work (LCM of 10, 12, 15) = 60 units. Efficiencies: A = 6, B = 5, C = 4. Total combined efficiency = 6 + 5 + 4 = 15 units/day. Time taken = 60 / 15 = 4 days.
Q6A can do a piece of work in 10 days and B can do the same work in 15 days. If they work together, in how many days will the work be completed?
A
5 days
B
6 days
C
8 days
D
9 days
Correct Answer: B
Explanation
A's 1-day work = 1/10, B's 1-day work = 1/15. Combined 1-day work = 1/10 + 1/15 = 5/30 = 1/6. Therefore, they will complete the work together in 6 days.
Q7A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete it?
A
6 days
B
7 days
C
8 days
D
9 days
Correct Answer: A
Explanation
Combined 1-day work = 1/4. A's 1-day work = 1/12. B's 1-day work = 1/4 - 1/12 = 2/12 = 1/6. Therefore, B alone can complete the work in 6 days.
Q8A is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
A
27 days
B
36 days
C
54 days
D
45 days
Correct Answer: A
Explanation
Ratio of work done by A and B = 2:1. Let B's 1-day work be x, so A's 1-day work is 2x. Together, 3x = 1/18, which means x = 1/54. A's 1-day work = 2 * (1/54) = 1/27. Thus, A alone completes it in 27 days.
Q9A, B, and C can complete a piece of work in 12, 15, and 20 days respectively. In how many days will they finish it together?
A
4 days
B
5 days
C
6 days
D
8 days
Correct Answer: B
Explanation
Total work = LCM of 12, 15, and 20 = 60 units. Efficiency of A = 5, B = 4, C = 3. Total efficiency = 5 + 4 + 3 = 12 units/day. Days required = 60 / 12 = 5 days.
Q10A can do a work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days will C alone finish the whole work?
A
24 days
B
30 days
C
25 days
D
40 days
Correct Answer: A
Explanation
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work done = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C's efficiency = 25 units / 10 days = 2.5 units/day. Days for C to complete total work = 60 / 2.5 = 24 days.
Q1112 men can complete a work in 8 days. How many days will it take for 16 men to complete the same work?
A
4 days
B
5 days
C
6 days
D
7 days
Correct Answer: C
Explanation
Using M1 * D1 = M2 * D2: 12 * 8 = 16 * D2. 96 = 16 * D2. D2 = 96 / 16 = 6 days.
Q12A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work?
A
24 days
B
25 days
C
30 days
D
35 days
Correct Answer: C
Explanation
A's 10-day work = 10/80 = 1/8. Remaining work = 7/8. B completes 7/8 work in 42 days, so B completes full work in 42 * (8/7) = 48 days. Combined 1-day work = 1/80 + 1/48 = (3 + 5)/240 = 8/240 = 1/30. They finish together in 30 days.
Q13If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same work?
A
4 days
B
3 days
C
2 days
D
5 days
Correct Answer: B
Explanation
3 Men = 6 Women => 1 Man = 2 Women. 12 Men + 8 Women = 12(2 Women) + 8 Women = 32 Women. If 6 women do it in 16 days, then 32 women do it in (6 * 16) / 32 = 3 days.
Q14A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days will A, B, and C finish it working together?
A
5 days
B
8 days
C
10 days
D
12 days
Correct Answer: C
Explanation
2(A + B + C)'s 1-day work = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. Therefore, (A + B + C)'s 1-day work = 1/10. Working together, they finish in 10 days.
Q15A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A
11 days
B
12 days
C
13 days
D
14 days
Correct Answer: A
Explanation
Total work = LCM(24, 30, 40) = 120 units. Efficiencies: A = 5, B = 4, C = 3. Total efficiency = 12 units/day. Since C left 4 days before completion, add the work C would have done in those 4 days: 120 + (3 * 4) = 132 units. Total days = 132 / 12 = 11 days.
FREE LIMIT REACHED
Unlock Remaining Questions
You've previewed 15 free questions.
Upgrade to unlock the remaining
431 questions in this topic,
plus 54,353+ MCQs and
All Premium Mock Tests.
1 Month Plan
₹49
₹49 / month
⭐ BEST VALUE
3 Months Plan
₹99
₹33 / month
6 Months Plan
₹149
₹24.83 / month
1 Year Plan
₹199
₹16.58 / month
Secure Purchase
Instant Activation
24×7 Support